by Heather Ellison | Dec 10, 2024 | Capital Campaign Updates
Key Points Fire Alarm Testing Friday Fire Alarm Testing Friday On Thursday, they will be testing the fire alarm for the CFM package. Please note that the alarm will sound and then immediately silenced. If the alarm persists after 30 seconds, please treat this as a...
by Heather Ellison | Dec 10, 2024 | Capital Campaign Updates
Key Points Traffic Flow Behind the Church on Thursday Worked Scheduled in Sanctuary & Wilson Chapel Next Week Traffic Flow Behind the Church Thursday The asphalt will be repaired this Thursday behind the church at the portico. During this repair, traffic will not...
by Heather Ellison | Dec 5, 2024 | Capital Campaign Updates
Key Points Lodge Elevator Closed Friday Fellowship Hall South Closes EOD Monday, December 9th until January Worked Scheduled in Sanctuary & Wilson Chapel Next Two Weeks Lodge Elevator Closed Friday, December 6 The Lodge Elevator will be painted tomorrow, Friday,...
by Heather Ellison | Nov 22, 2024 | Capital Campaign Updates
Key Points Power off in Wilson next Monday & Tuesday Wilson Chapel Building Power We will be doing needed electrical panel work next Monday and Tuesday – Nov 25 & 26 and will have to cut-off power to certain spaces. This will affect Wilson Chapel, the Parlor,...
by Heather Ellison | Nov 20, 2024 | Capital Campaign Updates
Key Points Gym Driveway Entrance Closed Tomorrow 1st Floor Main Entrance Doors Lodge Lobby Update: Gym Driveway Closed Tomorrow he entrance to campus at the Gym Building will be closed on Thursday, November 21st in order to install new thermal striping required by GA...
by Heather Ellison | Nov 19, 2024 | Capital Campaign Updates
Key Points Traffic Pattern Shift Next Week 1st Floor Hallway Closure (Columbarium Entrance) Gym Driveway Entrance Re-Striping Closure – On Hold Awaiting Reschedule Traffic Pattern Behind Church Shifts Monday-Wednesday In order to install piping and conduit necessary...