All Major Construction Packages are Complete.
The Central Plant Package and AHU Replacement Package Should Wrap Up by 2/28.
Quick Links
Special Projects Update #51
Key Points
- Fellowship Hall South Construction Area – DO NOT ENTER
- Thursday –Traffic Flows Behind the Church
- Saturday – No Power in 1200 Classrooms from 600-1200 hours
Fellowship Hall South Construction Area – Do Not Enter
The South Portion of the Fellowship Hall is a construction area. As a reminder, stay out of all construction areas. These areas are restricted access due to safety concerns and should not be entered under any circumstances.
Thursday – Filling Trench
The 70-ton crane has completed its work and is now off campus. Traffic free to pass behind the building. Tomorrow, Construction will be filling in the trench dug two week ago to connect the Cooling Towers plumbing lines to the sewer. Just like during the digging of the trench, the Construction team will keep traffic moving through the area in the back. The three parking spots next to the covered playground will be closed as well as the first 10 angled spots behind the portico. Please drive slowly and watch for directions from the workers in vests. This work should be completed by end of day, Thursday.
B-Panel Switchover
On Saturday between 600-1200 hours, we will be switching power source in the Preschool Area and Kitchen AHUs to the new Electrical Panel B. Power will be temporarily cut off to the 1200 classrooms and to the AHU’s in the kitchen. Power will be restored on Saturday and everything should be operable on Sunday morning.
Key Dates
September 2023
Fellowship Hall Re-Opens
May 2024
Staff Offices & New Belong Spaces Open
November 17, 2024
Sanctuary & Wilson Chapel Grand Re-Opening
January 24, 2025
CFM & Lodge Grand Re-Opening
Steeple Coffee Opens
All construction projects are moving targets. Please be flexible if dates and construction areas shift. Thank you.
Key Dates
September 2023
Fellowship Hall Re-Opens
May 2024
Staff Offices & New Belong Spaces Open
November 17, 2024
Sanctuary & Wilson Chapel Grand Re-Opening
January 24, 2025
CFM & Lodge Grand Re-Opening
Steeple Coffee Opens