St. Andrew’s Room Update
Due to a need for additional temporary shoring of the future freight elevator, the St. Andrews Room will be under construction Today-Friday. The construction team will be finished on Friday afternoon and the space will be ready for worship on Sunday.
Fellowship Hall Restroom Update
The restrooms on the 2nd floor outside the elevator will be unavailable on Thursday, November 2nd and Friday, November 3rd for the Tile Contractor to complete items on their Punch List. Thank you for your flexibility.
Key Dates
September 2023
Fellowship Hall Re-Opens
May 2024
Staff Offices & New Belong Spaces Open
November 17, 2024
Sanctuary & Wilson Chapel Grand Re-Opening
January 24, 2025
CFM & Lodge Grand Re-Opening
Steeple Coffee Opens