Key Points

  • Traffic Pattern Shift Next Week
  • 1st Floor Hallway Closure (Columbarium Entrance)
  • Gym Driveway Entrance Re-Striping Closure – On Hold Awaiting Reschedule

Traffic Pattern Behind Church Shifts Monday-Wednesday

In order to install piping and conduit necessary for the Central Plant Infrastructure Improvement Package, there will be different travel patterns at the back of the church.  Parking will not be available directly behind the church.  Please advise your groups to park in other areas of the church.  Also, please travel with caution behind the church and pay attention to the path you are traveling. It will be changing frequently.

 

Closure 1st Floor Hallway Between 1100 and 1200 Rooms

The Construction team will be closing the hallway between the two secured Preschool Entrances next Monday-Wednesday to paint and redo the stairs in that area. [Also know as the Columbarium entrance.]  Please use the exterior path to travel between the 1100 and 1200 building next week.

 

Gym Driveway Entrance Closure

Due to rain, the striping did not occur on Thursday, November 14th  at the Gym driveway entrance.  We are still awaiting the rescheduling of the striping.   I will let you know as soon as I am aware. Again, thank you for your flexibility as this necessary work is completed.

 

Key Dates

September 2023

Fellowship Hall Re-Opens

May 2024

Staff Offices & New Belong Spaces Open

November 17, 2024

Sanctuary & Wilson Chapel Grand Re-Opening

January 24, 2025

CFM & Lodge Grand Re-Opening
Steeple Coffee Opens

 

All construction projects are moving targets. Please be flexible if dates and construction areas shift. Thank you.