Key Points

  • REMINDER: Replacement of Main Hall Wood Flooring, 8/26-8/3

WOOD FLOORING REPLACEMENT OUTSIDE OF FELLOWSHIP HALL

IMPORTANT: Areas will be open on Sundays.

August 26-31

    • The main hallway will be CLOSED between the St. Andrews Room and the Flower Room to replace the Wood Floor installed during the Fellowship Hall package.
    • The hallway between the Williams Center and Fellowship Hall will be be closed.
    • Access to the larger Fellowship Hall Bathrooms, Kitchen, and the Flower Room may be gained by going through the Fellowship Hall, entering the 2nd floor Double Elevator Lobby.
    • The Williams Center Entrance will be closed during this period.

Key Dates

September 2023

Fellowship Hall Re-Opens

May 2024

Staff Offices & New Belong Spaces Open

November 17, 2024

Sanctuary & Wilson Chapel Grand Re-Opening

January 24, 2025

CFM & Lodge Grand Re-Opening
Steeple Coffee Opens

 

All construction projects are moving targets. Please be flexible if dates and construction areas shift. Thank you.