All Major Construction Packages are Complete.
The Central Plant Package and AHU Replacement Package Should Wrap Up by 2/28.
Quick Links
Special Projects Update #46
Key Points
- Fire Alarm Testing Friday
Fire Alarm Testing Friday
On Thursday, they will be testing the fire alarm for the CFM package. Please note that the alarm will sound and then immediately silenced.
If the alarm persists after 30 seconds, please treat this as a fire alarm and evacuate the building.
Key Dates
September 2023
Fellowship Hall Re-Opens
May 2024
Staff Offices & New Belong Spaces Open
November 17, 2024
Sanctuary & Wilson Chapel Grand Re-Opening
January 24, 2025
CFM & Lodge Grand Re-Opening
Steeple Coffee Opens
Traffic Flow Behind the Church Thursday
The asphalt will be repaired this Thursday behind the church at the portico. During this repair, traffic will not be able to go South behind the Portico. (You will not be able to drive from the Nursery to the Gym.) Traffic going North behind the church will continue to flow under the portico. (You will be able to drive from the Gym building to the nursery building.) Once the asphalt is repaired, we will be able to drive in both directions.
Key Dates
September 2023
Fellowship Hall Re-Opens
May 2024
Staff Offices & New Belong Spaces Open
November 17, 2024
Sanctuary & Wilson Chapel Grand Re-Opening
January 24, 2025
CFM & Lodge Grand Re-Opening
Steeple Coffee Opens
All construction projects are moving targets. Please be flexible if dates and construction areas shift. Thank you.
Key Dates
September 2023
Fellowship Hall Re-Opens
May 2024
Staff Offices & New Belong Spaces Open
November 17, 2024
Sanctuary & Wilson Chapel Grand Re-Opening
January 24, 2025
CFM & Lodge Grand Re-Opening
Steeple Coffee Opens