All Major Construction Packages are Complete.
The Central Plant Package and AHU Replacement Package Should Wrap Up by 2/28.
Quick Links
Special Projects Update #48
Key Points
- Wood Panel Work in Ambulatory – Monday
- Skylight Ceiling Repair – Friday/Saturday
- Chancel Wood Floor Repair – January 27/28
3rd Floor Ambulatory Area – Monday, 1/13
On Monday, our millwork subcontractor will be working on repairing the panel trim in the Ambulatory area. The work to be completed is on the wood paneling of the the two raised areas that allow access to the Sanctuary Chancel and Choir Loft. These areas are near the rear entrance of the freight elevator and Sacraments Room and then near the Finance Office entrance.)
Office Skylight Ceiling Repair – Friday/Saturday, 1/17-1/18
The contractor will be installing scaffolding on Friday in the staff break area in order to repair the ceiling at the skylight in the open office area.
Chancel Wood Floor – Sanctuary Blocked, 1/27-1/28
Damaged wood flooring planks will be switched out on the Sanctuary Chancel on Monday, 1/27 and Tuesday, 1/28. The Sanctuary will not be available for Funerals and Events these two days.
Key Dates
September 2023
Fellowship Hall Re-Opens
May 2024
Staff Offices & New Belong Spaces Open
November 17, 2024
Sanctuary & Wilson Chapel Grand Re-Opening
January 24, 2025
CFM & Lodge Grand Re-Opening
Steeple Coffee Opens
All construction projects are moving targets. Please be flexible if dates and construction areas shift. Thank you.
Key Dates
September 2023
Fellowship Hall Re-Opens
May 2024
Staff Offices & New Belong Spaces Open
November 17, 2024
Sanctuary & Wilson Chapel Grand Re-Opening
January 24, 2025
CFM & Lodge Grand Re-Opening
Steeple Coffee Opens