All Major Construction Packages are Complete.
The Central Plant Package and AHU Replacement Package Should Wrap Up by 2/28.
Quick Links
Special Projects Update #49
Key Points
- Fellowship Hall South–Closing February 3
- Traffic Flow Behind the Church
Fellowship Hall South – Closing
The mechanical equipment replacement in Fellowship Hall South for the roof-top unit has proven to require additional work of both steel and new piping. In order to accommodate Seeds of Hope and the Father/Daughter Dance, the south section of the Fellowship Hall was reopened this week. On Monday, February 3rd, the south section of the Fellowship Hall will re-close through the end of the month. Thank you for your flexibility in meeting in the North Section of the Fellowship Hall during this period.
Traffic Flow Behind the Church Monday-Wednesday
This Monday-Wednesday, the Construction team will be typing in a plumbing line from the Cooling tower to the sewer. The Construction team will keep traffic moving through the area in the back. The three parking spots next to the covered playground will be closed as well as the first 10 angled spots behind the portico. Please drive slowly and watch for directions from the workers in vests. Following Construction hours, plates will be placed on the driveway and the area will be open to traffic.
Key Dates
September 2023
Fellowship Hall Re-Opens
May 2024
Staff Offices & New Belong Spaces Open
November 17, 2024
Sanctuary & Wilson Chapel Grand Re-Opening
January 24, 2025
CFM & Lodge Grand Re-Opening
Steeple Coffee Opens
All construction projects are moving targets. Please be flexible if dates and construction areas shift. Thank you.
Key Dates
September 2023
Fellowship Hall Re-Opens
May 2024
Staff Offices & New Belong Spaces Open
November 17, 2024
Sanctuary & Wilson Chapel Grand Re-Opening
January 24, 2025
CFM & Lodge Grand Re-Opening
Steeple Coffee Opens