Staff Portal
At a Glance
All Major Construction Packages are Complete.
The Central Plant Package and AHU Replacement Package Should Wrap Up by 2/28.
Quick Links
Special Projects Update #50
Key Points
- Fellowship Hall South Closes Monday, February 3rd through the End of the Month
- Tuesday & Wednesday – No Thru Traffic Behind the Church between Portico and Loading Dock
Fellowship Hall South Closes Monday, February 3rd
At end of Day, Monday, February 3rd, Gay Construction restarts construction in the South Section of Fellowship Hall in order to replace the RTU (Roof Top Unit) above the space as part of our Air Handling Replacement Package. Entrances to the south section will be blocked at the Double Elevator Lobby, the St. Andrew’s Room, as well as the doors in the mobile partition.
Please remove any items you need prior to end of day Sunday. Any items left in the space will not be accessible again to the end of February.
Tuesday & Wednesday – No Thru Traffic Behind Church
A 70-ton crane will arrive on campus, Tuesday, February 4th and remain on campus through end of day Wednesday, February 5th. The RTU will be lifted off the roof and the new curb will be installed. For the crane and its outriggers, the area behind the church will be closed to through traffic. Guest parking by the Print Shop will be able to walk into the Main Entrance; however, guest parking near the Nursery will need to utilize another entrance.
Please notify your groups that are meeting next week to utilize parking in the Dogwood Parking Deck.
Key Dates
September 2023
Fellowship Hall Re-Opens
May 2024
Staff Offices & New Belong Spaces Open
November 17, 2024
Sanctuary & Wilson Chapel Grand Re-Opening
January 24, 2025
CFM & Lodge Grand Re-Opening
Steeple Coffee Opens
All construction projects are moving targets. Please be flexible if dates and construction areas shift. Thank you.
Key Dates
September 2023
Fellowship Hall Re-Opens
May 2024
Staff Offices & New Belong Spaces Open
November 17, 2024
Sanctuary & Wilson Chapel Grand Re-Opening
January 24, 2025
CFM & Lodge Grand Re-Opening
Steeple Coffee Opens